1Mobilisation
2Engineering
3Procurement
4Construction
5Installation
6Mech. Completion
7Commissioning
8O&M
9DLP
10Project Closeout
COMAPS / Why COMAPS

Why COMAPS?

Most contract failures are not caused by bad contractors. They are caused by contracts that were never properly understood — by anyone. COMAPS exists to fix that, before it becomes a problem.

The Contract Is Read Once — Then Filed

On most major EPC projects, the contract is reviewed at award and then rarely opened again. Obligations are not tracked. Hold Points are not enforced. Deviations are not formally raised. Evidence is not gathered contemporaneously.

By the time a dispute arises — or a Taking-Over Certificate is contested, or a DLP defect is denied — the project team no longer has the contemporaneous records needed to defend the Employer's position. The obligation existed. The breach occurred. The evidence was never captured.

COMAPS exists because contract management cannot be episodic. Every obligation must be identified before works begin, tracked through every phase, and closed with objective evidence. Not retrospectively — in real time, at every gate.

Where Projects Fail

  • Obligations discovered reactively — only when something goes wrong
  • Hold Points treated as advisory — waived under schedule pressure
  • NCRs raised informally and never formally closed with evidence
  • Submittals accepted without explicit ER clause references
  • Closeout is self-declared — the Contractor signs off its own work
  • The Employer's project record does not support the Employer's position

What COMAPS Does Instead

  • Every obligation identified, classified, and assigned before work starts
  • Hold Points administered as absolute contractual gates
  • NCRs tracked through the full PPVC lifecycle to evidenced closure
  • All submittals require explicit ER clause references — or are rejected
  • Closeout is evidence-based — not self-declared

What Makes COMAPS Different

There is no shortage of project management consultancies. What most do not bring is a systematic, obligation-by-obligation framework applied across all 12 management pillars, all 10 project phases, and every PPVC stage — simultaneously.

01 — Foundation
The Contract Is the Plan

COMAPS does not impose an external framework on top of the contract. The contract itself is the baseline. Every schedule, checklist, Hold Point, and performance metric derives directly from a contractual obligation.

02 — Completeness
All Pillars, All Phases

Most CMTs concentrate on HSE and Quality. COMAPS maps all 12 management pillars — H&S Management, ESG Management, Quality Management, Schedule Management, Risk Management, Interface Management, Communications Management, Change Management, HR Management, Security Management, Cost & Commercial Management, and Stakeholder Management — across all 10 project phases without exception.

03 — Control
The Gatekeeper Role

COMAPS does not manage the Contractor's works. It governs them. The CMT is the Gatekeeper between the EPC Contractor's execution and the Employer's formal acceptance — nothing advances without the gate being opened.

04 — Evidence
Records Are Contemporaneous

A project record assembled after the fact is a reconstruction. COMAPS generates contemporaneous evidence — daily diaries, inspection reports, signed Hold Point certificates, NCR registers — from day one. Every record is audit-ready from the moment it is created.

05 — Independence
Three-Party Discipline

EPC Contractor as Designer-Builder. Employer as Project Owner & Principal. CMT as Gatekeeper for the Employer. No party accepts its own work. No closeout is self-declared.

06 — Experience
Field-Proven, Not Theoretical

Every COMAPS specialist has delivered from the field on live international EPC projects. The methodology was refined under contract pressure, in real project environments, against real Contractor claims — not drawn from textbooks.

COMAPS Works for the Employer

COMAPS is engaged by the Employer — the party that has issued the contract and bears ultimate accountability for the project's success. The CMT sits on the Employer's side of the table throughout the project lifecycle.

Infrastructure Employers

Government agencies, development finance institutions, and private infrastructure owners commissioning major civil and energy works under international EPC contracts.

Energy Sector Owners

Project companies and concession holders delivering hydropower, thermal, transmission, and renewable energy projects where contractual compliance is tied to financial close conditions and lender reporting requirements.

Development Finance

Multilateral lenders and development banks requiring independent oversight of contractor performance, environmental compliance, and disbursement-linked milestone verification across the project lifecycle.

One Framework — Every Obligation, Every Phase

PPVC is not a project stage. It is the operating cycle that governs every obligation, across every pillar, at every phase. Before any activity starts: Plan. During execution: Perform. After completion: Validate. Before closeout: Complete.

Stage The CMT Question Gate Condition Failure to Comply
PLAN Are we ready to start? Approved plans, RAMS, and ITPs in place. Hold Points identified. Named focal points assigned. Works do not commence. Hold Point remains locked.
PERFORM Is the work being done as planned? Execution matches approved method. CMT witnesses critical activities. Daily diary updated. NCR raised. Works suspended pending corrective action.
VALIDATE Does evidence prove compliance? Test results reviewed. As-built records confirmed. All NCRs closed with objective evidence. Formal acceptance withheld. Follow-on works blocked.
COMPLETE Is this activity ready for handover? Sign-off issued. ER checklist completed. TOC recommended on evidence — not declaration. Certificate not recommended. Deficiency list remains open.

COMAPS vs. Business as Usual

The table below reflects what COMAPS consistently observes when engaged on a project where contract management has been left to the EPC Contractor and an understaffed Employer team.

Area Without COMAPS With COMAPS
Obligation Identification Discovered reactively — when something goes wrong 100% identified, classified, and assigned before works start
Hold Points Treated as advisory — waived under schedule pressure Absolute contractual gates — no works proceed without formal written CMT acceptance
NCR Management Informal verbal resolution — no audit trail Formal PPVC lifecycle — raised, tracked, validated, evidenced, closed
Project Record Assembled retrospectively — incomplete and inconsistent Built contemporaneously from day one — audit-ready at every stage
Closeout Self-declared by the Contractor — not independently verified Evidence-based — CMT recommends TOC only when all conditions are fully met
Dispute Position Employer lacks contemporaneous records to support its position Complete traceable record — every obligation evidenced, every gate signed

Four Pages — One Complete System

Contract Review identifies the obligations. Mapping assigns every obligation to a pillar and phase. Performance tracks execution in real time. Strategies protect the position when things go wrong.

01 Contract ReviewsSix-lens review · 10 phases · 12 pillars · FIDIC compatibility 02 Action MappingObligation registers · WBS · ITP structure · ER checklist format 03 Performance ComplianceLive checklists · PPVC gates · NCR lifecycle · KPI regime 04 Strategies & ProtectionRisk register · Notices · Change management · Dispute avoidance

Why COMAPS — In Summary

Discuss Your Project →