COMAPS / Performance of Activities

Performance of Activities — COMAPS

Every project phase produces outputs. Every output has an obligation. Every obligation is tracked against the mapped compliance framework — from the first design submission in Engineering through to the last defect resolved in the DLP.

Performance Starts at Mobilisation — Not Construction

Performance of activities is not limited to physical works on site. Mobilisation is when COMAPS deploys — the contract is reviewed, pillars are assigned, and the framework is activated. Engineering produces design deliverables that require CMT review and acceptance. Procurement produces supplier approvals, material certificates, and Factory Acceptance Tests. Each phase has a defined output set — each output is tracked against the mapped compliance checklist. The CMT's management role is active from day one of the contract.

Phase Primary Outputs Tracked CMT Action Gate
02 · Engineering Design submissions, calculations, drawings, BIM model, Design Criteria Memorandum, Basic & Detailed Design packages Review and issue Category A/B/C response within contractual period. Track design freeze milestones against Baseline Schedule. Design Acceptance Hold Point
03 · Procurement Supplier qualifications, material submittals, inspection test records, Factory Acceptance Test certificates, expediting reports Approve suppliers, witness or waive FATs, review material certificates, track long-lead procurement against ITP gates. Supplier & FAT Hold Points
04 · Construction RAMS, site inspection records, concrete/material test results, ITP sign-offs, subcontractor compliance records Daily site presence, approve RAMS, attend Hold/Witness Points, raise NCRs for deviations, upload site diary to EDMS within 24hrs. Construction ITP Hold Points
05 · Installation Equipment installation records, alignment & levelling certificates, pre-wiring inspection, loop check records Attend installation Hold Points, review installation method statements, verify certificates before pre-commissioning. Installation Readiness Hold Point
06 · Mech. Completion System completion certificates, punch list, pre-commissioning test records, snag register Review and accept system completion evidence, sign off punch list, confirm readiness for commissioning. MC Certificate Hold Point
07 · Commissioning Commissioning plan, performance test records, operational test sign-offs, reliability run records Accept commissioning plan, witness performance tests, review test results, recommend Taking-Over Certificate to Employer. Taking-Over Hold Point
08 · O&M Operations handover records, O&M manuals, as-built drawings, training completion records Review and accept O&M documentation, verify training completion, confirm handover conditions are met. Handover Hold Point
09 · DLP Defect register, defect remediation evidence, annual inspection records, DLP expiry notification Maintain defect register, attend annual inspections, verify remediation evidence, recommend Performance Certificate. Performance Certificate Hold Point
10 · Project Closeout Final account, close-out report, lessons learned register, all EDMS records archived Review final account, confirm all NCRs closed, confirm all checklists signed off, issue CMT close-out recommendation. CMT Close-Out Certificate — All Obligations Compliant

All Twelve Pillars — Tracked and Evidenced at Every Phase

Every management pillar identified during contract review and mapped during the mapping phase is actively tracked during performance. Each pillar has a named CMT lead, a live compliance checklist, and a reporting obligation. Nothing is passive. Nothing is assumed. The following defines what performance looks like for each pillar.

H&S Management
  • RAMS reviewed and approved before each activity
  • Toolbox talks verified and logged
  • Incident log maintained daily
  • Stop-work authority enforced without exception
ESG Management
  • Environmental monitoring actioned per plan
  • Community liaison meetings attended
  • Grievance register active and reviewed
  • E&S reports submitted within timescales
Quality Management
  • ITP progressed activity by activity
  • NCRs raised formally — no informal acceptance
  • Material approvals tracked against schedule
  • Test certificates filed per ER clause
Schedule Management
  • Progress measured against Baseline — not contractor revision
  • S-curve updated monthly, 6-week look-ahead weekly
  • Delay events logged in real time
  • Recovery plans required formally
Risk Management
  • Risk register reviewed and updated monthly
  • New risks assessed, registered, and assigned
  • Mitigation actions tracked to closure
  • Risk owner accountability enforced
Interface Management
  • Interface register updated and circulated
  • Third-party coordination meetings attended
  • Interdependency conflicts raised formally in writing
  • Interface hold points tracked and enforced
Communications Management
  • All formal correspondence logged in EDMS <24hrs
  • Notice register maintained throughout project
  • Meeting minutes with actions distributed <48hrs
  • Communications protocol applied without exception
Change Management
  • Change register maintained from first notification
  • No uninstructed works executed
  • Variation Orders issued before scope changes
  • Cumulative variation impact reviewed monthly
HR Management
  • Monthly labour returns reviewed and verified
  • Local employment targets tracked against ER obligation
  • Key personnel competence monitored
  • Training records checked and filed
Security Management
  • Daily access control records maintained
  • Security incidents logged and reported
  • Security plan compliance verified
  • CMT unrestricted access to all site areas enforced
Commercial Management
  • Contract sum tracked against earned value monthly
  • Payment certificates assessed independently
  • Deductions and contra-charges substantiated in writing
  • Final account prepared from EDMS records
Stakeholder Management
  • Stakeholder register maintained and updated
  • Engagement actions logged and evidenced
  • Escalations managed through formal correspondence
  • Monthly stakeholder report issued to Employer

Phase 04 · Construction — Quality Pillar · PPVC Tracking Extract

The following is an illustrative extract from a COMAPS Performance Compliance Checklist — Construction phase, Quality pillar. Every obligation mapped during the Engineering/Procurement phases is tracked here through the PPVC lifecycle. Each row carries a live PPVC status and an evidence reference. Nothing is marked Complete without a signed document or field record in the EDMS.

COMAPS Performance Compliance Checklist
Phase 04 · Construction Pillar Quality Vol 3.8 · Concrete Works CMT Lead A. Williams
PPVC Key: PPlanned PPerformed VValidated CComplete Pending
# Clause Obligation Type PPVC Status Evidence Ref CMT Sign-Off
01 Vol. 3.8 §3.1
Concrete Mix Design — Submit & Obtain CMT Acceptance
Contractor submits mix design for all permanent concrete classes (C20, C25, C30, C35). CMT reviews against ER specifications and issues Category A/B/C response. Hold Point — no concrete batching until acceptance issued.
H
P P V C
CLOSED
COMAPS-QA-2024-0043
Cat A Acceptance — 14 Mar 2024

14 Mar 24
02 Vol. 3.8 §5.2
Concrete Placement — Block 4A Foundation Slab — ITP H-03
Pre-pour inspection including reinforcement, formwork, embedments, and cleanliness. Concrete placement, vibration, and curing. CMT to attend and sign ITP Hold Point H-03 before concrete is placed.
H
P P V
IN REVIEW
COMAPS-ITP-2024-H03
Cube tests pending — 21d results due 12 Apr

Pending
03 Vol. 3.8 §6.1
Concrete Cube Tests — 7-day, 21-day, 28-day Results to CMT
Contractor submits cube test certificates for each pour. CMT reviews against ER minimum strength requirements. Repeated failures at 28-day trigger NCR and works suspension. Review Point per pour.
R
P P
IN PROGRESS
COMAPS-LAB-2024-0107
7-day certs received. 21-day pending.

Active
04 Vol. 3.8 §7.4
Curing Regime — Non-Conformance NCR-2024-031
ER requires minimum 7-day wet curing for all structural concrete. Site inspection on 22 Mar found curing removed at day 4 on Block 4A East wall. NCR raised. CAP submitted by Contractor — CMT review in progress.
W
P !
NCR OPEN
NCR-2024-031
CAP submitted 25 Mar — CMT review due 28 Mar

NCR
05 Vol. 3.8 §9.1
Concrete Core Samples — Post-Hardening Verification
Where 28-day cube test results are borderline or NCR raised, CMT may require core extraction and independent laboratory testing. Core results govern — Contractor cannot dispute without alternative CMT-approved evidence.
R
NOT STARTED
Conditional on NCR-2024-031 outcome
Pending
Section Sign-Off Contractor Representative: ___________________ CMT Team Lead: A. Williams Date: ___________
Works may not proceed to Phase 04 until both parties sign

Illustrative extract — format applied to all 12 management pillars across all 10 project phases. Each obligation carries a PPVC status and an evidence reference. Nothing is marked Complete without an EDMS-filed, CMT-signed document.

Hold Point · Witness Point · Review Point — Three Levels of Oversight

Every engineering, procurement, and construction activity is governed by an ITP approved during the mapping phase. Each entry carries one of three designations. These are contractual — they cannot be downgraded unilaterally by the Contractor. They apply from the first design submission to the final commissioning test.

Designation Definition CMT Obligation Works Proceed?
H — Hold Point Mandatory contractual gate. Works suspended until formal written CMT acceptance is issued. Attend, inspect, and issue written acceptance. 48hrs advance notice required. Failure to notify does not waive the Hold Point. No — written acceptance required.
W — Witness Point CMT has the contractual right to attend and witness. Works proceed only with written CMT waiver. Attend or issue written waiver. 24hrs notice required. Evidence filed regardless of CMT attendance. Only with written CMT waiver.
R — Review Point CMT reviews submitted records, certificates, or test results. Physical attendance not required. Issue Category A/B/C response within the agreed review period. Works may proceed after submission. Yes — after submission.

NCR — Raised, Actioned, Evidenced, Closed

An NCR is raised whenever works, materials, submittals, or management outputs deviate from the approved ITP, RAMS, or ER. The NCR applies to all phases and all pillars — a non-conforming design submission triggers an NCR the same as non-conforming concrete. No NCR is closed without objective evidence of resolution accepted by the CMT.

PLAN
  • NCR raised with unique reference
  • Non-conformance described with ER clause reference
  • Root cause analysis required from Contractor
PERFORM
  • Corrective Action Plan submitted by Contractor
  • CMT reviews and accepts or rejects the CAP
  • Remedial action executed under CMT observation
VALIDATE
  • CMT inspects or reviews remedial output
  • Evidence package reviewed — tests, photos, records
  • Re-test or re-submission if ITP requires it
COMPLETE
  • CMT issues formal written close-out
  • NCR register updated in EDMS
  • Lessons learned recorded and distributed

Continuous Audit Trail — Evidence-Based Close-Out

The performance phase generates an unbroken audit trail from day one of Engineering to the last page of the close-out report. At close-out, the completed checklist suite across all 12 pillars is the compliance record — not a summary, but a signed, verified account of every obligation.

Reporting Cadence

  • Weekly site / coordination meetings — progress, open NCRs, upcoming Hold Points, pillar status
  • Monthly Progress Report — submitted within 7 days of month end, reviewed and commented by CMT
  • Monthly S-curve — actual vs baseline, submitted with MPR
  • Quarterly risk register review across all 9 risk categories
  • All meeting minutes with action items, owners, and due dates — distributed within 48 hours

Close-Out Conditions

  • All compliance checklist sections signed off across all 12 management pillars
  • All NCRs formally closed — zero outstanding entries at Taking-Over
  • All ITP Hold Points signed off — master ITP register complete
  • As-built drawings, O&M documentation, and test records submitted and accepted
  • Taking-Over Certificate recommended by CMT — not self-declared by Contractor

Summary