Every project phase produces outputs. Every output has an obligation. Every obligation is tracked against the mapped compliance framework — from the first design submission in Engineering through to the last defect resolved in the DLP.
Performance of activities is not limited to physical works on site. Mobilisation is when COMAPS deploys — the contract is reviewed, pillars are assigned, and the framework is activated. Engineering produces design deliverables that require CMT review and acceptance. Procurement produces supplier approvals, material certificates, and Factory Acceptance Tests. Each phase has a defined output set — each output is tracked against the mapped compliance checklist. The CMT's management role is active from day one of the contract.
| Phase | Primary Outputs Tracked | CMT Action | Gate |
|---|---|---|---|
| 02 · Engineering | Design submissions, calculations, drawings, BIM model, Design Criteria Memorandum, Basic & Detailed Design packages | Review and issue Category A/B/C response within contractual period. Track design freeze milestones against Baseline Schedule. | Design Acceptance Hold Point |
| 03 · Procurement | Supplier qualifications, material submittals, inspection test records, Factory Acceptance Test certificates, expediting reports | Approve suppliers, witness or waive FATs, review material certificates, track long-lead procurement against ITP gates. | Supplier & FAT Hold Points |
| 04 · Construction | RAMS, site inspection records, concrete/material test results, ITP sign-offs, subcontractor compliance records | Daily site presence, approve RAMS, attend Hold/Witness Points, raise NCRs for deviations, upload site diary to EDMS within 24hrs. | Construction ITP Hold Points |
| 05 · Installation | Equipment installation records, alignment & levelling certificates, pre-wiring inspection, loop check records | Attend installation Hold Points, review installation method statements, verify certificates before pre-commissioning. | Installation Readiness Hold Point |
| 06 · Mech. Completion | System completion certificates, punch list, pre-commissioning test records, snag register | Review and accept system completion evidence, sign off punch list, confirm readiness for commissioning. | MC Certificate Hold Point |
| 07 · Commissioning | Commissioning plan, performance test records, operational test sign-offs, reliability run records | Accept commissioning plan, witness performance tests, review test results, recommend Taking-Over Certificate to Employer. | Taking-Over Hold Point |
| 08 · O&M | Operations handover records, O&M manuals, as-built drawings, training completion records | Review and accept O&M documentation, verify training completion, confirm handover conditions are met. | Handover Hold Point |
| 09 · DLP | Defect register, defect remediation evidence, annual inspection records, DLP expiry notification | Maintain defect register, attend annual inspections, verify remediation evidence, recommend Performance Certificate. | Performance Certificate Hold Point |
| 10 · Project Closeout | Final account, close-out report, lessons learned register, all EDMS records archived | Review final account, confirm all NCRs closed, confirm all checklists signed off, issue CMT close-out recommendation. | CMT Close-Out Certificate — All Obligations Compliant |
Every management pillar identified during contract review and mapped during the mapping phase is actively tracked during performance. Each pillar has a named CMT lead, a live compliance checklist, and a reporting obligation. Nothing is passive. Nothing is assumed. The following defines what performance looks like for each pillar.
The following is an illustrative extract from a COMAPS Performance Compliance Checklist — Construction phase, Quality pillar. Every obligation mapped during the Engineering/Procurement phases is tracked here through the PPVC lifecycle. Each row carries a live PPVC status and an evidence reference. Nothing is marked Complete without a signed document or field record in the EDMS.
| # | Clause | Obligation | Type | PPVC Status | Evidence Ref | CMT Sign-Off |
|---|---|---|---|---|---|---|
| 01 | Vol. 3.8 §3.1 |
Concrete Mix Design — Submit & Obtain CMT Acceptance
Contractor submits mix design for all permanent concrete classes (C20, C25, C30, C35). CMT reviews against ER specifications and issues Category A/B/C response. Hold Point — no concrete batching until acceptance issued.
|
H |
P
P
V
C
CLOSED
|
COMAPS-QA-2024-0043 Cat A Acceptance — 14 Mar 2024 |
✓ 14 Mar 24 |
| 02 | Vol. 3.8 §5.2 |
Concrete Placement — Block 4A Foundation Slab — ITP H-03
Pre-pour inspection including reinforcement, formwork, embedments, and cleanliness. Concrete placement, vibration, and curing. CMT to attend and sign ITP Hold Point H-03 before concrete is placed.
|
H |
P
P
V
—
IN REVIEW
|
COMAPS-ITP-2024-H03 Cube tests pending — 21d results due 12 Apr |
⧖ Pending |
| 03 | Vol. 3.8 §6.1 |
Concrete Cube Tests — 7-day, 21-day, 28-day Results to CMT
Contractor submits cube test certificates for each pour. CMT reviews against ER minimum strength requirements. Repeated failures at 28-day trigger NCR and works suspension. Review Point per pour.
|
R |
P
P
—
—
IN PROGRESS
|
COMAPS-LAB-2024-0107 7-day certs received. 21-day pending. |
◎ Active |
| 04 | Vol. 3.8 §7.4 |
Curing Regime — Non-Conformance NCR-2024-031
ER requires minimum 7-day wet curing for all structural concrete. Site inspection on 22 Mar found curing removed at day 4 on Block 4A East wall. NCR raised. CAP submitted by Contractor — CMT review in progress.
|
W |
P
!
—
—
NCR OPEN
|
NCR-2024-031 CAP submitted 25 Mar — CMT review due 28 Mar |
✗ NCR |
| 05 | Vol. 3.8 §9.1 |
Concrete Core Samples — Post-Hardening Verification
Where 28-day cube test results are borderline or NCR raised, CMT may require core extraction and independent laboratory testing. Core results govern — Contractor cannot dispute without alternative CMT-approved evidence.
|
R |
—
—
—
—
NOT STARTED
|
Conditional on NCR-2024-031 outcome | ○ Pending |
Illustrative extract — format applied to all 12 management pillars across all 10 project phases. Each obligation carries a PPVC status and an evidence reference. Nothing is marked Complete without an EDMS-filed, CMT-signed document.
Every engineering, procurement, and construction activity is governed by an ITP approved during the mapping phase. Each entry carries one of three designations. These are contractual — they cannot be downgraded unilaterally by the Contractor. They apply from the first design submission to the final commissioning test.
| Designation | Definition | CMT Obligation | Works Proceed? |
|---|---|---|---|
| H — Hold Point | Mandatory contractual gate. Works suspended until formal written CMT acceptance is issued. | Attend, inspect, and issue written acceptance. 48hrs advance notice required. Failure to notify does not waive the Hold Point. | No — written acceptance required. |
| W — Witness Point | CMT has the contractual right to attend and witness. Works proceed only with written CMT waiver. | Attend or issue written waiver. 24hrs notice required. Evidence filed regardless of CMT attendance. | Only with written CMT waiver. |
| R — Review Point | CMT reviews submitted records, certificates, or test results. Physical attendance not required. | Issue Category A/B/C response within the agreed review period. Works may proceed after submission. | Yes — after submission. |
An NCR is raised whenever works, materials, submittals, or management outputs deviate from the approved ITP, RAMS, or ER. The NCR applies to all phases and all pillars — a non-conforming design submission triggers an NCR the same as non-conforming concrete. No NCR is closed without objective evidence of resolution accepted by the CMT.
The performance phase generates an unbroken audit trail from day one of Engineering to the last page of the close-out report. At close-out, the completed checklist suite across all 12 pillars is the compliance record — not a summary, but a signed, verified account of every obligation.